Fire Recovery Update
- Virginia Callegary
- Aug 27
- 1 min read
As of August 25, 2025
Good news on the repair front:
The Structural Engineer will be submitting design plans to the County for approval that are much simpler than what we were originally lead to believe. The design does not require the need for custom made trusses that have an 8 to 10 week timeframe to manufacture. The steel for the repair is readily available at any steel supply house. Additionally, the plan calls for repairing the trusses from below and not making extensive cuts to the Sanctuary floor. The current estimate to complete the repairs is now six months.